It all started when I mentioned that it might be nice to
have a separate place where I could go and watch TV or read or play on the Wii…I
said that I’d also like a second bathroom and I’d like a utility room.
I wanted to convert the animal barn on the side of our house
(accessed through the kitchen) into a ‘snug’.
After a few months of persuasion Peter was in. We looked for a builder (traumatic enough,
read the blog post) we found the one we wanted and work was scheduled for
January 2014.
In December 2013 I started to take down the old bread oven
in the corner of the room. A mass of
stones, red clay, and 50 year old soot.
I’d come out looking like I’d been down a mine. Our 90 year old neighbour sat on her step
and laughed at me. She was still
grinning when finally the oven was dismantled and I carried hundreds of stone
down the 14 steps to the stairwell for storage. It wouldn’t be the last time I moved those
stones!!!
January came, Mark and Rupert our builders came, so did the
rain. In fact, it didn’t stop raining.
They did what they could.
Took down and rebuilt a wall.
Removed the rotten and bug infested beams in the place. Started work on the new bathroom. I started to clean the natural stone wall. The
floor was levelled with the large stones removed and a concrete base put
in. Peter carried hundreds of buckets of
concrete up 14 steps in the rain. But
soon they all had to stop, the roof needed to come off and it just would not
stop raining.
February came and went in a mixture of rain, hail and
thunder. I kept cleaning the natural
stone wall. A wire brush and a heap of
patience (which quickly turned into impatience), I soon realised why restoration work is so
time consuming. ‘Render the whole lot’
became my mantra.
March arrived and so did the builders. Off came the roof. On went a new roof. Suddenly we had a dry room. I was still cleaning the natural stone wall
as my first attempt was ‘not good enough’ according to some.
Work continued on the new bathroom, and work started on the
megalith chimney Peter designed. It was
then that I was asked to bring all the stones from the bread oven stored in the
stairwell back up the 14 steps and into the snug. Following a few very choice four letter
words I started to grade the stones and bring these up.
Work continued on the chimney, it was getting bigger and
bigger. An intricate air flow system was
installed, including a hole in the wall to draw in air, a hole in the top to
let out air and a fan into the bedroom to pump warm air upstairs. The chimney got bigger.
May came and the builders went off site to start another
project. We had some work that needed
to be done, like cleaning the natural stone wall. Leveling and concreted the public path
behind our house and waterproofing one of the snug walls (which is below ground
level).
We had the doors and windows fitted.
In late May the builders returned, the chimney got bigger,
the new bathroom got tiled. The rendering started. It was starting to become a real room, four
walls, windows, doors and floor. Peter carried buckets of concrete up the
stairs, I cleaned up after people, washing and washing the floor in the
connecting kitchen (dirty work this building work). ‘It looks like a building site’ was the
mantra for a while.
In June, disaster struck.
Our builders had to go off and finish another job. They’d be back in July to finish up the
work. I had planned to get them to
redesign our upstairs bathroom too.
But one of the builders almost cut his fingers off in a wood saw and
while he was healing there was no way he’d be able to finish the rendering (he
since made a full recovery).
July came, impatience set in. ‘Find another builder, I just want it
finished’ became my mantra. ‘I’m fed up
with this’ became Peter’s.
In August, Duncan came to finish the job. Duncan finished the rendering, pointed the
natural stone wall (which meant I had to clean the whole bloody thing again)
and tiled the stairs and the utility room floor.
Work started on the ceiling. If only it was that easy. The ceiling beams were not level, we’d
decided to keep some of the old wood and the whole thing just couldn’t be
plaster boarded unless we wanted a ‘wave effect’ on the ceiling.
Peter put his thinking cap on and came up with a
plan….’we’ll fit the plaster board between the beams’ he said. After three weeks I bet he wished he’d come
up with another idea. Every day he was in
there cutting board to the strange shape of the room. Not a straight wall in sight. Now I certainly understand why they knock
down old walls and rebuild and don’t restore walls.
I cleaned the lime cement mix from the natural stone wall.
I got covered in plaster as I sanded the plaster board. I broke the sander.
Duncan had done all he could do. It was now up to us. Paint, varnish, paint, varnish. Peter continued with the ceiling. Filling the gaps in between the plasterboard
and the wood, he varnished the wood. I painted
the bathroom, not well.
I painted the walls a little better. Peter delicately painted around the
stones.
In September I went away for 2 weeks and the floor elves
(Peter and Simon) put in the wooden floor.
We are almost there, bear with me.
Just the snagging to do, Peter
worked his socks off. Varnishing,
filling, touching up and then spent what seemed like hours trying to get the
fibre optic cable working.
Finally we moved in. We love it.
The fire heats up the room in about 10 mins, the dog sits on his bean
bag in the corner and finally we can sit at a table to eat our dinner.
My Wall |
It does leave the other room a
little under used. But Peter has a plan,
he wants a nice kitchen-diner.
I am open to persuasion!
Oh wow! The house is really shaping up nicely. I love the quaint appeal of the low ceiling and the fireplace. I'm sure the space will look absolutely amazing once everything is finished. Thank you so much for sharing the update! Wishing you all the best with the rest of the work!
ReplyDeletePleasance Faast @ Shelton